Tuesday, July 15, 2008
More Eco-friendly photos


Finished slab


The pour
At about 2/3rds poured, the second truck was supposed to show up with the remaining concrete. It got lost. When it finally showed up, it had been on the road for 2 and 1/2 hours!! Needless to say, there were surface cracks in the second part of the slab even though I had ordered polyester fibers in the concrete. Bummer. So far, the livingroom is perfect (and the area under the stairs, big deal). The kitchen floor is going to have "character."
The threshold forms were foamed into place. I wrote on them "NOT A STEP." That worked about five minutes and then the concrete workers were walking on them. They held up, thankfully, and popped right out when removed. On the lower right is the worker's breakfast. Not shown is the beer that accompanied it.

The mud is then screeded with a board. This is the second use for the 2x4s that were used for the FastFooter. 
Then comes the bull float. Gorden Boyer, the pump operator, got his bull float out and gave some lessons on the livingroom pad.


Stamped concrete
Hydronics details

Wednesday, July 09, 2008
He's back!
Ready for hydronics
Here's the vapor barrier all taped down. It's a 15 mil product, so you don't create pinhole leaks when walking on it. Then, we put down the foam, and that is covered with 6x6" remesh, more for laying out the hydronic tubes than for strength in the slab.


The tubing is Pex-Al-Pex, meaning that it's a layer of Pex plastic, a layer of aluminum, then a layer of Pex. This does two things. First, when bent it stays bent. No wrestling with trying to tie down a tube that wants to spring back into a coil. Second, the aluminum acts as an oxygen barrier to protect the circulation equipment when the system is complete.



The tubing is Pex-Al-Pex, meaning that it's a layer of Pex plastic, a layer of aluminum, then a layer of Pex. This does two things. First, when bent it stays bent. No wrestling with trying to tie down a tube that wants to spring back into a coil. Second, the aluminum acts as an oxygen barrier to protect the circulation equipment when the system is complete.
Tuesday, July 01, 2008
Slab preparation



I now know why I have a dip in
one area on the footer. I didn't notice it until I started using this 16' board as a screed on the sand. I should have checked this out when setting up the forms. Better yet, when buying the lumber. Actually, the curve occured after removing the board and throwing it in a pile. Be careful to keep your lumber stickered properly so that it doesn't warp before you use it for the forms.

Little Kubota saves shovel work.

Dam that ICCF

Putting in the under-slab DWV

Two drains on an interior wall. This is where a non-bearing wall will end up that runs from the slab all the way to the attic. It was the perfect place for my DWV system to go from one floor to the next, but it was a little scary having the pipes come up through the slab. That ensured that the wall position was "cast in stone" (actually, cast in concrete).

You can also see at the bottom right of the picture the copper ground wire and a 3/10 wire going out the the well pump. Because of the slab on grade construction, the electrical also came in under and through the slab. It makes for a very clean look, since I and my neighbors all have underground electrical service, but it also has to be accurately planned.


You can also see at the bottom right of the picture the copper ground wire and a 3/10 wire going out the the well pump. Because of the slab on grade construction, the electrical also came in under and through the slab. It makes for a very clean look, since I and my neighbors all have underground electrical service, but it also has to be accurately planned.